(1) The Federal Government may in any Province construct or cause to be constructed hydro-electric or thermal power installations or grid stations for the generation of electricity and lay or cause to be laid inter-Provincial transmission lines : 12Provided that the Federal Government, prior to taking a decision to construct or cause to be constructed, hydro-electric power stations in any Province, shall consult the Provincial Government concerned.

(2) The Government of a Province may —

(a) to the extent electricity is supplied to that Province from the national grid, require supply to be made in bulk for transmission and distribution within the Province;

(b) levy tax on consumption of electricity within the Province;

(c) construct power houses and grid stations and lay transmission lines for use within the Province; and

(d) determine the tariff for distribution of electricity within the Province.

3(3) In case of any dispute between the Federal Government and a Provincial Government in respect of any matter under this Article, any of the said Governments may move the Council of Common Interests for resolution of the dispute.

JUS.smart answers from the text of this Article and the records on this site, and names the Articles it read.

Previous: Article 156Next: Article 158

History of this article

3 changes recorded.

From the official consolidation of the Constitution published by the Ministry of Law and Justice (Fourteenth Edition), as amended to 21 November 2025: its footnotes, and for an omitted article the words that record the omission. Each note is reproduced as printed. The line above it names the instrument it refers to.

  1. 1

    Substituted · Eighteenth Amendment, 2010

    Subs. by the Constitution (Eighteenth Amdt.) Act, 2010 (10 of 2010), s. 58, for the full-stop.

  2. 2

    Inserted · Eighteenth Amendment, 2010

    Proviso ins.ibid.

  3. 3

    Added · Eighteenth Amendment, 2010

    New clause (3) added ibid.

In Reconstituting Public Power

Article 157 in the five Books.

Khurram Chughtai's discussion of this article: the Topics that address it, with the sentence that names it, the author's doctrines they apply and the judgments their notes rely on. Drawn from the text by machine; each Topic opens in the reader.

  1. Topic 122The Supreme Court (Constitution of 1956, arts 148 to 163)Chapter 5, The 1956 Constitution and the Crisis of Federal SettlementComposition and appointment. Article 157 gave an appeal from a judgment, decree or final order of a High Court in civil, criminal or other proceedings where the High Court certified that the case involved a substantial question of law as to the interpretation of the Constitution, with power in the Supreme Court to grant…
  2. Topic 130A constitution written around the administrationChapter 6, The 1962 Constitution and the Presidential Administrative StateWhat the instrument was, and who made it. The adult citizen of twenty-one was enrolled upon the roll of an electoral unit (Articles 156 and 157).
  3. Topic 146Electoral units and the Elector (Constitution of 1962, arts 155 to 158)Chapter 6, The 1962 Constitution and the Presidential Administrative StateWhere the provisions sit. Article 157 entitled any citizen not less than twenty-one years of age, not of unsound mind, and resident or deemed by law to be resident in an electoral unit, to be enrolled upon that unit’s roll, except as provided by law.
  4. Topic 664Mixed functions and cross-provincial responsibilitiesChapter 25, Federal Public Power and Shared RuleCompetence must be decided before exemption. Article 157 governs electricity and refers disputes between governments to the Council of Common Interests.
  5. Topic 670Fiscal capacity and provincial resource entitlementsChapter 26, Provincial Public Power and Provincial AutonomyProvincial shares have constitutional protection. Under Article 157(2) a Province may, to the extent electricity is supplied to it from the national grid, require supply in bulk for transmission and distribution within the Province; it may also levy tax on consumption of electricity within the Province, construct power houses and grid stations and…
  6. Topic 675The National Economic Council and the National Finance CommissionChapter 27, Intergovernmental Power: Councils and Shared AuthorityNational planning has an advisory setting. Article 157 offers a concrete example of differentiated authority within a shared system.
  7. Topic 677Water, electricity and the resolution of disputesChapter 27, Intergovernmental Power: Councils and Shared AuthorityWater complaints include harmful omission. Article 157(1) permits the Federal Government to construct hydro-electric or thermal power installations or grid stations in a Province and to lay inter-Provincial transmission lines, but its proviso requires prior consultation with the Provincial Government concerned before a decision to construct…
  8. Topic 714Competing settlements and the test of allocationChapter 31, Principles for Allocating Public PowerTest the complete allocation. Article 157(3) permits either the Federal Government or the Provincial Government concerned to refer a dispute between them in respect of a matter under that article to the Council for resolution.
  9. Topic 803Taxation and the distribution of burdensChapter 40, Fiscal Power as Constitutional PowerArticle 77 makes legislation the source. Neither side pursued the Article 157 issue in the Supreme Court, which dismissed the appeals without endorsing the High Court’s reasoning.
  10. Topic 812Revenue effort, autonomy and resource entitlementsChapter 41, Federal–provincial Fiscal Settlement and the NFCTax competence, administration and receipt are separate. Article 157 makes separate provision for federal and provincial electricity powers and permits a government to move the Council of Common Interests upon a dispute under that Article.
  11. Topic 891Succession must preserve services, rights and connected systemsChapter 52, Territorial Reorganisation Impact AssessmentAssets and liabilities require an inventory and a lawful allocation. The constitutional provisions must be read separately: Article 155 concerns interference with water supplies, Article 157 electricity, Article 158 qualified precedence for the Province of a natural-gas well-head, Article 161 specified revenues and hydro-electric net profits, and Article 172(3)…
  12. Topic 897Hazara, recognition, language and alternativesChapter 53, Regional Application StudiesA provincial name and provincial membership are distinct questions.

The twelve Topics that discuss Article 157 most closely are shown, of 13 in 11 chapters.

Doctrines of the author applied

  • Means of performance2 Topics discussing Article 157 · first stated in Topic 1
  • Authority–capacity correspondence1 Topic discussing Article 157 · first stated in Topic 310
  • Structural exploitation1 Topic discussing Article 157 · first stated in Topic 26
  • Reconstitution, not reallocation1 Topic discussing Article 157 · first stated in Topic 17
  • Self-Sustaining Constitutional Capacity1 Topic discussing Article 157 · first stated in Topic 795

Judgments relied on

  • Sindh Revenue Board v Civil Aviation Authority of Pakistan 2017 SCMR 1344cited in 2 notes
  • Lucky Cement Ltd v Federation of Pakistan PLD 2011 Peshawar 57cited in 2 notes
  • Government of Sindh v Dr Nadeem Rizvi 2020 SCMR 1cited in 2 notes
  • Karachi Electric Supply Company Ltd v National Industrial Relations Commission PLD 2014 Sindh 553cited in 1 note
  • Cherat Cement Company Ltd v Pakistan PLD 2016 Peshawar 32cited in 1 note
  • Federation of Pakistan v Agritech Ltd PLD 2016 SC 676cited in 1 note
  • Engineer Iqbal Zafar Jhagra v Federation of Pakistan 2013 SCMR 1337cited in 1 note
  • Cyanamid Pakistan Ltd v Collector of Customs PLD 2005 SC 495cited in 1 note
  • Government of Pakistan v Muhammad Ashraf PLD 1993 SC 176cited in 1 note
  • All Pakistan Textile Mills Association v Province of Sindh 2004 YLR 192cited in 1 note
  • Messrs Elahi Cotton Mills Ltd v Federation of Pakistan PLD 1997 SC 582cited in 1 note
  • Workers’ Welfare Funds v East Pakistan Chrome Tannery (Pvt) Ltd PLD 2017 SC 28cited in 1 note